Organizing a renovation? Learn the steps for efficient execution
The order of services during renovation is key to avoiding headaches and unnecessary rework, ensuring a more fluid and efficient process.
By Chrys Hadrian
Updated at Feb 26, 2024, 3:12 PM - Submitted at Feb 27, 2024, 9:00 AM
08 min de leitura
(pvproductions/Freepik/)
Renovating your home can be an exciting yet challenging journey. From the initial decision to completion, there are a number of important steps to consider to ensure everything goes according to plan.Knowing the correct order of services can make all the difference in efficient and trouble-free execution . Below, we present the essential steps that, with the appropriate guidance and supervision of specialized architects and professionals , will certainly guarantee satisfactory and long-lasting results.
(pvproductions/freepik / CASACOR)
1st - Installation/Modification of electrical and hydraulic points and opening of gapsBefore starting any other stage, it is crucial to deal with the structural modifications that involve breaking down walls, floors and removing coverings. This phase lays the foundation for all subsequent interventions, ensuring that the infrastructure is suitable for future needs.2nd - Waterproofing of wet areasReplacing ceramic coatings in areas subject to humidity or carrying out hydraulic modifications requires special attention to waterproofing. This step is essential to prevent leaks and long-term structural damage.3rd - Changing ceramic coatingsWith the structural modifications complete, it’s time to install the new coverings. It’s essential to ensure precise and careful application for a flawless, long-lasting finish.4th - Application of fillerIf necessary, apply or touch up the putty on the walls to correct imperfections and obtain a smooth, uniform surface before the final painting.
(freepic.diller/freepik / CASACOR)
5th - Preparation for electrical installationsBefore proceeding with any assembly, make sure that the electrical infrastructure is ready, including the proper position of power and lighting points.6th - Installation of plaster elementsWith the electrical installations ready, it's time to install plaster elements, such as lowered ceilings and moldings, adding a touch of elegance to the environment.7th - Painting and finishing the wallsAfter applying the plaster and putty, it is time to sand and paint the surfaces, providing a visually attractive and long-lasting finish.8th - Installation of floor coveringsInstall floor coverings, such as laminate, and protect them properly during the rest of the work. This step adds comfort and beauty to the space.9th - Installation of light fixtures and lighting pointsInstall the lights, leaving only those centered on specific furniture until after assembly. Proper lighting is essential to create pleasant and functional atmospheres.10th - Furniture and countertop assembly
(tonodiaz/Freepik / CASACOR)
11th - Stone installationOnce the furniture is assembled or part of it is finished, proceed with the installation of stones, such as granite and marble. Make sure that the stones are cut and finished before installation to avoid damage to the furniture and the structure.12th - Installation of skirting boardsInstall baseboards, prioritizing areas that do not have furniture. This step adds a stylish visual finish and protects walls from impacts and moisture.13th - Installation of boxes and mirrorsThe installation of shower enclosures and mirrors should take place at this point, taking into account the final measurements after the furniture has been assembled. This ensures a precise fit and a harmonious appearance.14th - Metal installationCall a plumbing professional to install metal fixtures, such as faucets and valves. Take care to avoid leaks and damage to furniture during this step.15th - Installation of household appliancesInstall equipment such as stoves, heaters and ovens to complete the functionality of the rooms. Check that all connections are correct and secure.16th - Painting touch-upsMake the final touches to the paintwork, correcting any imperfections that may have arisen during the work. Inform the painter about the need for these adjustments to ensure a flawless finish.
(Freepik / CASACOR)
17th - Heavy cleaningBefore unpacking and arranging furniture and decorations, thoroughly clean the entire space. Use suitable products that will not damage materials and surfaces.18th - Curtains and wallpapersInstall curtains and wallpaper according to the established decoration plan. These details add personality and warmth to the spaces.19th - Loose furniture and decorationsFinally, organize the loose furniture and decorations, personalizing the spaces according to your taste and style. Take the opportunity to get inspired and create functional and welcoming spaces.
(Freepik / CASACOR)
Following these steps in order will ensure an organized and hassle-free renovation, resulting in renovated spaces ready to be enjoyed. Always remember to rely on qualified professionals and quality materials for a satisfactory end result .